Pre-requisite for
this step: Below deliverables should
be available for this step
1. Work Packages identified
2. Activity list that describe each of the activities are defined
3. Activity sequencing that describe how each of the activities are related to each other are clear
4. Quantity, Type and category of the resources required to complete the activity is clear
Contingency Reserves are approved for Known and Risks (i.e. Known unknowns) where risk response strategy is approved by steering committee - These efforts are included as part of schedule baseline
Project Efforts = Schedule Baseline Efforts + Manager Reserve Efforts
1. Work Packages identified
2. Activity list that describe each of the activities are defined
3. Activity sequencing that describe how each of the activities are related to each other are clear
4. Quantity, Type and category of the resources required to complete the activity is clear
Objective of this
step: Estimate the number of work periods needed to complete individual
activities with estimated resources.
That is we will detail the amount of time each activity will take to
complete
1. Outputs:
Activity Duration Estimates
- Likely work periods that are required to complete the activity. These do not
include any lags/leads. For example, the
activity estimate can be:
2 weeks +/- 2 days:à
Activity will at least take 8 working days and the maximum it takes 12 working
days (assuming a five day work sheet)
Project Document
Updates - Activity Attributes - Assumptions made in developing the activity
duration estimates, such as skill levels and avaialability and basis of
estimate durations
2. Tools
and Techniques:
A. Expert Judgement
– Guided by historical information, Expert Judgement can provide duration
estimate information from prior similar projects.
B. Analogous
Estimating - Analogous in English Language means Similar, Equivalent, and
Comparable. Thus, we take similar
projects executed in the past and adjust current differential requirement
sizing through expert Judgement – Similarity can be complexity, weight, size,
budget and duration - Thus it is Top
Down Approach based on historical similar previous project experience - -
Adjusted for current project complexity. Less Accurate -Less Time taking - best
suited for ball park estimates where less info is available. Most reliable when
previous projects are similar in fact not just in appearance. When
limited information is available, Analogous estimating is best adopted
approach. It is less costly and less time consuming and less accurate. It is more reliable only when the previous
projects we take are similar in the fact not just in the appearance.
C. Parametric Estimation: An algorithmic
model is built based on parameters and historical info. An algorithm is used to
calculate cost, duration based on historical data and project parameters.
Example, Per Square Foot cost in construction, Function Points, use case
points. Lines of Code etc. Once
parameter is arrived, then it is aggregated to Duration and Cost based on
historical info available. It can produce
higher levels of accuracy depending on the underlying model accuracy. This
can be applied either to total project or particular phases of project.
D. Three Point
Estimation: Considers Estimation uncertainty
and involved risks. It can be done in two ways
Triangular
Estimation
|
Beta/PERT
Estimation
|
Duration = {Most Likely + Optimistic (best case scenario)+
Pessimistic [Worst case Scenario]}/3
|
Duration = (Most Likely +
4*Optimistic + Pessimistic)/6
|
Equal probability for Most likely, Optimistic and Pessimistic
estimates exists (i.e. 33.33%)
|
Un Equal Probability for Most likely, Optimistic and Pessimistic
estimates exists. Most likely is
probable by 67% and rest of the estimates are probable by 16.5%
|
E. Group Decision
making techniques: Brainstorming - Delphi techniques for engaging team
members to improve estimate accuracy and commitment to the emerging estimates.
F. Reserve Analysis:
Contingency Reserves are approved for Known and Risks (i.e. Known unknowns) where risk response strategy is approved by steering committee - These efforts are included as part of schedule baseline
Schedule Baseline Effort = Activity Efforts + Contingency
reserve efforts
Management Reserve - For Unknown Unknowns (i.e. For Unknown
Risks) (eg. Calamity, Earth Quake) - Not included as part of schedule baseline. Management reserve efforts are taken trough Change control procedureProject Efforts = Schedule Baseline Efforts + Manager Reserve Efforts
3. Inputs:
Schedule Management Plan - Activity List - Activity
Attributes- Activity Resource Requirements - Resource Calendars - Project Scope
statements - Risk Register [List of Risks, along with results of risk analysis,
risk response planning, Updates to risk register] - Resource Break Down
Structure - Enterprise Environmental Factors [Productivity Metrics, Duration
Estimation Data, Published commercial info, Location of team members] - Org
Process Assets [Historical info - Lessons Learnt- Scheduling Methodology-
Project Calendars]
No comments:
Post a Comment